Fisher Elementary Construction
Fisher Elementary Construction
Posted on 11/15/2016
Fisher Elementary ConstructionConstruction News - August 2017 

    Crews are working diligently to get Fisher ready for the first day of school.  Most things will be done and the school will be ready to welcome students on August 31st.  However, there are items that will need some more time so we will be a work in progress for a bit longer than planned.

    If you were to visit the school today (August 21) you would see most things nearing completion.

    On the exterior:

    • The parking lot surface is complete and ready for striping
    • The sidewalks are complete and landscaping is being finalized
    • The siding and painting on the exterior is almost complete and should be done by the end of the week
    • The covered play shed is getting the final touches to be ready for rainy days
    • The bus loop behind the school is in progress and we hope to have it ready by the first day of school.  We will have an alternate plan for bus drop off for a couple of days if it is not done in time.


    On the interior:

    • The cleaning crew is working to dust, sweep, mop, and wipe down all surfaces
    • The gym floor is complete and bleachers will be installed this week
    • The carpet is going in offices, classrooms, and the library
    • Almost all the cabinets are installed (we are waiting for a small shipment to arrive this week to finish the job)
    • Fire and safety alarms are being tested as well as phones and technology


    Things happening this week:

    • School supplies and materials are being moved into offices and classrooms
    • Furniture is being delivered and put into offices and classrooms
    • Teachers can start working and preparing rooms


    Fisher Offices at the new school will open on August 28th
    .

    • Families are welcome to come to the office to take care of all necessary items at that time.  There will be a time on the 31st for students to come to meet their teachers and see their classrooms.  Please be on the lookout for more details in a communication from Principal Courtney Ross.

    Remember that the east end includes 4 additional classrooms that were added after the project began and will be completed in January.

    We will have a grand opening on September 12th from 6:30-8:00 – We will have coffee and snacks and the school will be open to explore.

     

     


Perspective View